What Is a Pay Less Notice? Subcontractor Guide
What Is a Pay Less Notice? A Subcontractor's Guide to the Construction Act Rules
Few documents frustrate subcontractors more than a pay less notice. It tends to land a few days before you expect to be paid and cuts the figure you were counting on, sometimes to nothing. The rules behind it are strict, though, and a notice that is late, vague or aimed at the wrong application can often be challenged.
This guide explains how a pay less notice works under the Construction Act and JCT subcontracts, and what you can do when the main contractor gets it wrong. It covers the position in England and Wales.

What Is a Pay Less Notice and When Must It Be Issued?
A pay less notice is a written notice from the paying party, usually the main contractor, saying it intends to pay less than the notified sum. Under section 111 of the Housing Grants, Construction and Regeneration Act 1996 (the Construction Act), it must state the sum the payer considers due and the basis on which that sum has been calculated. It must be served no later than the prescribed period before the final date for payment.
The notified sum is normally the figure in the main contractor's payment notice. If no valid payment notice was issued, it becomes the figure in your payment application or default payment notice.
The prescribed period is whatever your subcontract says. If the subcontract is silent, the Scheme for Construction Contracts fills the gap and sets it at 7 days before the final date for payment.
To be valid, the notice should:
- be in writing and served in the way the subcontract requires
- state the amount the payer considers due, even if that amount is zero
- explain how that amount has been calculated
- relate clearly to a specific payment application or payment cycle
- make plain that it is intended to operate as a pay less notice
The courts judge these notices on substance rather than form. In RBH Building Contractors v James (2026), the Court of Appeal held that an ordinary letter stating an intention to pay nothing, with bullet points explaining which parts of the claim were disputed, was a valid pay less notice. So a notice is not invalid just because it lacks the right heading. Equally, in Advance JV v Enisca (2022), a notice that did not clearly respond to the correct application failed, leaving the payer liable for around £2.7 million.
Payment Notices vs Pay Less Notices: How the Construction Act Payment Timeline Works
A payment notice and a pay less notice do different jobs. The payment notice says what the payer believes is due. The pay less notice says the payer intends to pay less than the notified sum, whatever that turns out to be. The required content is almost identical, which is why the timing matters so much.
Each payment cycle follows the same sequence:
- Due date. The date payment becomes due under the subcontract. Under the Scheme, this is 7 days after the valuation date or your application, whichever is later.
- Payment notice. The main contractor must issue this no later than 5 days after the due date, setting out the sum it considers due and how it was calculated.
- Default payment notice. If no payment notice arrives, your application stands as the notified sum where the subcontract allows it. Otherwise, you can serve your own default notice, which pushes back the final date for payment by the same number of days it was late.
- Pay less notice. The last chance for the main contractor to reduce the notified sum, served no later than the prescribed period before the final date for payment.
- Final date for payment. The deadline for paying the notified sum, or the sum in a valid pay less notice. Under the Scheme, it is 17 days after the due date.
Taking the Scheme defaults, a valuation date of the 1st gives a due date of the 8th. The payment notice is due by the 13th, the final date for payment is the 25th, and any pay less notice must be served by the 18th.
The TCC has also confirmed that a payment notice and a pay less notice can be sent together, provided they are separate notices, and that a pay less notice can be served at any point after your application has been made (Placefirst Construction v CAR Construction, 2025).
One trap catches main contractors regularly. Courts have confirmed that the final date for payment must be a fixed period after the due date. Where a subcontract ties it to receipt of a VAT invoice or some other event, the Scheme's 17-day period can apply instead, and a notice served against a longer contractual timetable may be out of time. This is one reason to have payment terms checked before you sign, alongside the clauses in our guide to 5 unfair subcontract terms to be wary of.
Pay Less Notices Under JCT Contracts
Unamended JCT 2016 contracts and subcontracts require any pay less notice to be given no later than 5 days before the final date for payment, which is usually 14 days after the due date. The payment notice must still be issued within 5 days of the due date. The 2024 JCT editions keep the same five-day period.
In practice, many main contractors amend these timings. Final dates for payment of 21, 28 or 30 days are common, and some subcontracts allow one to be served as little as one day before the final date. Those amendments are lawful if you agree to them, so the dates that apply to your account are the ones in the signed subcontract, not the standard form. Our contract advice and support service reviews these terms before you commit to them.
That may change. The Commercial Payments Bill, which was still going through Parliament at the time of writing, would stop parties agreeing a notice period shorter than 7 days before the final date for payment.
The same notice rules apply to the final payment as well as interim valuations. Under some JCT forms, a final statement becomes conclusive if it is not disputed in time, so the notice deadlines at the end of a job deserve as much attention as the monthly cycle. If your account is still unresolved, our final account services can help.
What Happens If a Valid Pay Less Notice Is Not Served?
If the main contractor fails to serve a valid pay less notice in time, it must pay the notified sum in full by the final date for payment. It cannot simply deduct contra-charges or withhold money because it disagrees with your valuation.
If the money is not paid, you have two main options:
- Refer the dispute to adjudication. A claim for an unpaid notified sum is often called a smash and grab adjudication, and it usually turns on dates and documents rather than the true value of the work. Our guide to adjudication in construction explains how the process works.
- Suspend performance. After giving at least 7 days' written notice, you can suspend some or all of your work. You are entitled to your reasonable costs of suspending and to an extension of time for the period of suspension.
A smash and grab win is not always the final word. Following S&T v Grove (2018), the paying party can start its own adjudication on the true value of the work, but only after it has paid the notified sum. You get the cash first, and any argument about value happens afterwards.
Do not assume every flawed notice can be knocked out. Courts will uphold a notice that is tolerably clear, and they have refused to treat a late payment notice as a pay less notice after the event (Vision Construction v Gypcraft, 2025). The strength of your position depends on the exact dates and wording.
When a notice arrives, it is worth checking:
- the date it was received against the final date for payment in your subcontract
- whether it states a sum and explains how that sum was calculated
- which application or payment cycle it responds to
- whether your subcontract's payment terms comply with the Construction Act at all
A pay less notice is a strict, date-driven tool. If the main contractor serves it properly, you will usually need to argue about the true value of your work. If it does not, you may be entitled to the full notified sum straight away.
RJH Consulting has represented subcontractors in more than 200 adjudications. If you have received a pay less notice you think is invalid, or no notice at all, talk to us about our construction adjudication services or wider construction dispute resolution support. Call 01347 811155 or email info@rjhconsulting.co.uk.