What Is Adjudication in Construction? A Guide | RJH Consulting
Admin Access

What Is Adjudication in Construction? A Subcontractor's Step-by-Step Guide

What Adjudication Means


In simple terms, adjudication is a fast-track way to resolve a construction dispute. Instead of going to court, which can take months or years, you put your case to an independent adjudicator, who reviews the evidence from both sides and issues a decision within 28 days.


That decision is binding straight away. If you win, the other party has to pay you, even if they're unhappy with the outcome and want to challenge it later through the courts. In practice, this makes adjudication one of the most effective tools a subcontractor has for unlocking cash that's being wrongly withheld.


Adjudication is most commonly used for disputes over non-payment, unjustified deductions, contra-charges, extensions of time, and loss and expense claims — the exact issues that most often affect subcontractor cash flow.


Your Statutory Right (Construction Act 1996)


Here's the part most subcontractors don't realise: you don't need permission to use adjudication, and you don't need your contract to specifically allow it.


The Housing Grants, Construction and Regeneration Act 1996 (often called "the Construction Act") gives either party to a qualifying construction contract the statutory right to refer a dispute to adjudication at any time. Even if your subcontract is silent on the subject, or tries to exclude it, the law implies this right into the contract automatically.


This is what makes adjudication so powerful it's not a favour the main contractor grants you, it's a legal entitlement you already have.


The Step-by-Step Timeline


  1. Notice of Adjudication: You (or your representative) serve a formal notice setting out the dispute and what you're claiming.
  2. Adjudicator appointed: An independent adjudicator is appointed, usually within 7 days, often via a nominating body such as the RICS or CIArb.
  3. Referral submitted: You submit your full case within 7 days of the notice — your evidence, valuation, and legal/contractual basis for the claim.
  4. Response: The other party submits their response, disputing or accepting points as they see fit.
  5. Reply: You have the opportunity to reply to any new points they've raised.
  6. Decision: The adjudicator issues a binding decision within 28 days of the referral (extendable by 14 days with your agreement).


From start to finish, most adjudications are resolved in around a month, dramatically faster than litigation or arbitration.


Adjudication vs Arbitration vs Litigation


Adjudication — Fast (28 days), lower cost, binding immediately (though it can later be challenged through litigation or arbitration if either party pursues it). Best suited to payment and contractual disputes that need resolving quickly.

Arbitration — A private process similar to court, but conducted by an arbitrator rather than a judge. Typically used where the contract specifies it, or for more complex, higher-value disputes. Slower and more costly than adjudication.

Litigation — Formal court proceedings. The most thorough route, but also the slowest and most expensive — often taking a year or more, with legal costs to match.

For most subcontractor payment disputes, adjudication offers the best balance of speed, cost, and enforceability — which is why it's used far more often than the other two routes.


What It Costs


Costs vary depending on the complexity of the dispute and who represents you, but broadly:


  • The adjudicator's fees are typically split between both parties, or awarded against the losing party at the adjudicator's discretion
  • If you use a specialist consultant, fixed-fee and no-win-no-fee arrangements are often available, giving you cost certainty upfront
  • Solicitors typically bill hourly, which can make costs less predictable

Because adjudication is fast, total costs are usually far lower than litigation or arbitration simply due to the shorter timeframe involved.


What Happens After the Decision


Once the adjudicator issues their decision, it's binding immediately the paying party must comply, typically within 7 days unless the decision states otherwise.


In the vast majority of cases, that's the end of the matter: the decision is paid and the dispute is resolved. If the other party refuses to pay, the decision can be enforced through the courts via a summary judgment process, which is generally quick and difficult to resist.


Either party can still pursue litigation or arbitration afterwards if they want the dispute reconsidered on a final basis but in practice, this is relatively rare, because most parties treat the adjudicator's decision as final.


Getting Help


You don't have to run an adjudication yourself. Most subcontractors bring in a specialist to prepare the notice, build the referral, and manage the process end to end, so you get the outcome without the time drain.



RJH Consulting has represented subcontractors in over 200 adjudications, with consistent success recovering payment that was wrongly withheld. If you think you might have a case, a free strategy session is the fastest way to find out.



Talk to an Adjudication Specialist
A man with a beard wearing a white shirt and purple tie
Richard Hildrick - Founder
BSc(Hons) MSc MRICS MCIOB FCIArb

A book titled 10 things you must know to avoid and resolve construction payment disputes
By Admin Access August 14, 2026
A sample blog post from RJH Consulting, York-based specialists in construction law, adjudication and commercial support for subcontractors.
Why denton contractors trust rjh is written on a red background
August 21, 2024
How a Specialist Subcontractor Benefitted from Adding RJH to Its Team, and Upped its Commercial and Contractual Game Overnight.
A man is giving a presentation to a group of people in a conference room.
August 20, 2024
Our workshops are tailored to each company’s requirements, ensuring you and your team get the most out of it, at a fixed price. One previous attendee said the workshop was: “Vital to anyone working in a commercial or project management role in construction, to understand the workings and thinking of main contractors today.”
An aerial view of a construction site with a lot of buildings and cranes.
By Richard Hildrick August 19, 2024
NEC Contracts Early Warnings v Compensation Events
A man in a yellow jacket is holding a book.
By Richard Hildrick July 24, 2024
Discover how RJH Consulting uses adjudication to recover unpaid contra-charges and deductions for subcontractors, including a recent case worth over £200,000.
A group of construction cranes are silhouetted against a cloudy sky.
By Richard Hildrick June 25, 2024
A cautionary tale from RJH Consulting about a main contractor who levied unfair contra-charges on his subcontractor, and how the dispute was resolved.
A large room with tables and chairs in it.
June 30, 2021
For our latest client, boxxe, we managed a £1m+ office redesign project commercially and operationally. The result was a sleek, modern and on-budget project, completed over a 30-week period.
A construction worker is holding a roll of blueprints.
By RJH Consulting April 15, 2021
Download RJH Consulting's free guide to the 20 most common commercial problems subcontractors face, with practical advice on how to resolve each one.
A man is writing on a piece of paper with a pen.
April 15, 2021
Template Documents to make Subcontractor's lives easier when managing their projects.
Looking up at a group of skyscrapers against a blue sky.
By Richard Hildrick February 10, 2021
Find out how the construction industry's reverse charge VAT rules affect contractors and subcontractors, and what you need to do to stay compliant.