CONSTRUCTION MANAGEMENT  |  BUILDING & INFRASTRUCTURE WORKS

Loss & Expense Claims - Recover Prolongation & Disruption Costs

Delayed or Disrupted Through No Fault of Your Own? Claim the Costs Back


When a project overruns or gets disrupted because of someone else's failure, delayed information, late access, instructed changes, it's usually the subcontractor who absorbs the extra cost. Extended time on site, idle labour, extra supervision, none of that is free, and you shouldn't be the one paying for it.


Loss and expense claims exist precisely for this. Done properly, with the right records and the right valuation, they can recover a substantial amount. Done badly, or not submitted at all, that money is simply lost.



GET IN TOUCH

“Richard proved to be extremely knowledgeable and proficient in resolving our financial problem with a prominent, nationwide, but particularly difficult Client. His efficiency in dealing with the situation prevented the exacerbation of further problems, allowing a swift and successful outcome for our Company. We would have no hesitation in recommending his expertise to anyone in a similar situation."
 

– David Cook. M.D., H. Smith Electrical

Solution / Process / Agreement / Testimonials

What Loss & Expense Covers

Loss and expense is the mechanism for recovering the direct financial loss caused by matters that are, contractually, not your fault, things like delayed instructions, late access to the site, variations, or disruption caused by the main contractor or other trades.



It typically covers costs such as extended preliminaries, idle plant and labour, additional supervision time, and increased costs caused by the delay itself, for example if material prices moved during the extended period. It doesn't cover delay that's your own responsibility.



JCT vs NEC Entitlement


The route to recovery depends heavily on your form of contract.


Under JCT contracts, loss and expense is usually claimed under the relevant clause once you've given notice that regular progress has been, or is likely to be, materially affected. You then need to submit the application with supporting information for the ascertainment of the amount.


Under NEC contracts, the mechanism works through compensation events. Instead of a separate loss and expense claim, you notify a compensation event and submit a quotation showing the effect on cost and time. Timing is stricter under NEC, notices generally need to be raised within a set number of weeks of becoming aware of the event, or you can lose entitlement entirely.



Getting this distinction right matters. Treating an NEC contract like a JCT one, or missing an early warning notice, is one of the most common ways subcontractors lose entitlement they'd otherwise have had.




A man wearing a yellow jacket that says rjh on it
Richard Hildrick - Founder
BSc(Hons) MSc MRICS MCIOB FCIArb

Start The Process


GET IN TOUCH
Book a FREE Project Review or call:
01347 811155

Prolongation vs Disruption


These are often used interchangeably, but they're not the same thing, and a claim usually needs to address both separately.


Prolongation is the cost of the project simply running longer than planned, extended site overheads, supervision, plant hire, and so on, calculated over the additional period.


Disruption is the loss of productivity or efficiency caused by the disrupting event, even where the overall programme hasn't necessarily been extended. It's usually harder to prove and needs a different method of valuation, often based on measured productivity loss rather than simply extended time.



Records You Need


Claims live or die on evidence. The records that matter most are:


  • Programme information, both as-planned and as-built
  • Site diaries and daily records showing what actually happened and when
  • Correspondence, instructions, and any early warning or notice you issued
  • Labour and plant allocation records for the affected period
  • Photographic evidence where relevant



If you're not already keeping this level of record on site, it's worth starting now, even before a claim is on the table. It's far easier to build a claim from good contemporaneous records than to reconstruct events months later from memory.



How We Build & Value the Claim


RJH prepares the claim from the ground up: establishing entitlement under your specific contract, pulling together the supporting records, and producing a valuation that a main contractor's QS will actually engage with rather than dismiss out of hand.


Where the claim needs to go further, whether that's negotiation, mediation or adjudication, we run that process too, so you're not handing it off to someone new partway through.

Worked Example


To give a sense of scale: a subcontractor delayed by eight weeks due to late main contractor information might reasonably claim extended site overheads (say, a site manager and welfare costs for that period), plant standing time, and increased costs where material prices rose during the extension. On a mid-size project, that kind of claim can run into tens of thousands of pounds, money that's very rarely paid automatically and almost always requires a properly evidenced application to recover.



This is illustrative only. Every claim is different, and the actual value depends entirely on your specific records and contract.



A man wearing a yellow jacket that says rjh on it
Richard Hildrick - Founder
BSc(Hons) MSc MRICS MCIOB FCIArb

Start The Process


GET IN TOUCH
Book a FREE Project Review or call:
01347 811155

Get Your Claim Valued


If you've been delayed or disrupted and haven't submitted a claim, or you're not confident the one you've submitted is being taken seriously, get it reviewed properly.

Book A Free Strategy Session
A white background with a few lines on it
“RJH has a robust approach defending our position and achieving our objectives when dealing with all the contractors, quietly and effectively invoked. We also have comfort that there is experience in dispute resolution which should prevent our project requiring those services, and we have benefited from the consistency of working with one person throughout”

Richard Mole

Project Co-ordinator, Driffield Methodist Church
A white background with a few lines on it
“I found Richard Hildrick to be supremely professional, innovative in his thinking yet remaining clear and concise. In a matter of weeks, Richard had outthought the other side and obtained a reduction of over 35% on what was being sought by the main contractor on his final account.”

Arthur Wilby

Managing Director
A white background with a few lines on it
“Richard proved to be extremely knowledgeable and proficient in resolving our financial problem with a prominent, nationwide, but particularly difficult Client. His efficiency in dealing with the situation prevented the exacerbation of further problems, allowing a swift and successful outcome for our Company. We would have no hesitation in recommending his expertise to anyone in a similar situation.”

David Cook

M.D. - H. Smith Electrical

"Our goal is to ensure that you obtain the building work that you want, on time and within budget, without suffering any adverse impact on your business."

A man wearing a yellow jacket that says rjh on it
Richard Hildrick - Founder
BSc(Hons) MSc MRICS MCIOB FCIArb
A book titled the risks and pitfalls associated with your construction project and how to overcome them
Do you have a vision of new or improved built facilities to enable your operations to grow and flourish, but don’t know how to go about realising your vision?

Are you thinking of refurbishing, altering, or enlarging an existing building? Or would you like to create a new-build facility for your organisation from scratch? 
    Do you have little or no experience of the commercial construction process, and are concerned about any of the following:

    • You don’t really understand the construction process and worry about getting it wrong
    • You fear that costs for your project might exceed your budget or spiral out of control
    • You’re concerned about poor quality work, ‘cowboy builders’, and ultimately not getting the facility which your organisation needs
    • You worry there could be an adverse impact on your existing business
    • The regulations, red-tape, and risks involved seem like insurmountable barriers
    Whatever construction works you have in mind to move your organisation forward to greater success, our highly experienced team of construction project management professionals will help you to take your ambitions from your initial vision, right through to putting your new facilities into operation.

    At RJH, we believe that you shouldn’t have to suffer from sub-standard work, rip-off prices associated with the construction industry, or what at times can seem like a completely bewildering process.

    Our goal as UK construction consultants is to ensure that you obtain the building work that you want, on time and within budget, without suffering any adverse impact on your business or a substantial drain of your time and energy from having to navigate through complex regulations, deal with numerous consultants and contractors, and manage all of the inherent risks at the same time.

    Appointing the right Contractor is a minefield and things can quickly go wrong resulting in escalating costs, poor quality of work, delays and substantial hassle. The good news is that we understand exactly how to get the physical work designed, procured and completed professionally for you, in compliance with all Regulations, meeting your requirements, with minimum risk, and giving you value for your investment.

    If you need support and advice with any or all of the following, we are on hand to help you whatever stage your project is at:Project Management (from inception to completion or any stage in between)
    • Design of your construction project (via the selection and appointment of appropriate professionals)
    • Planning Permission, Building Regulations, and CDM Regulations
    • Quantity Surveying - Costing of the proposed construction works and Cost Management throughout the design and construction processes
    • Drawing up Tender documents and obtaining competitive tenders from suitably qualified Contractors
    • Advising on and drafting Contracts for the Construction works and for design Consultants.
    • Project or Construction Management during the construction phase
    • Employer’s Agent role
    • Principal Designer role
    • Value Engineering
    We are construction management industry professionals – Chartered Surveyors and Chartered Construction Managers, with over 30 years' experience of procuring and successfully completing large building and civil engineering construction projects. We will support and guide you through the entire process and remove the burden of overcoming the many risks and challenges it poses. Ultimately, you will enjoy the benefit of a building which has met your expectations in all respects.

    Our parallel expertise in construction dispute resolution gives you additional peace of mind. We know everything that can go wrong and are therefore best placed to spot potential issues, pitfalls and conflict well before it happens, ensuring that what could go wrong, doesn't.

    We guarantee to reduce the stress and risk associated with managing your construction project to a successful conclusion, allowing you to concentrate your time and energy on running your business – contact us now to book a free initial project review.
    FREE Project Review
    A book titled the risks and pitfalls associated with your construction project and how to overcome them

    The Risks and Pitfalls Associated With Your Construction Project, And How To Overcome Them

    Inside you'll learn...
    • How to navigate the various application, approval and sign‐off processes at the relevant stages of your project.
    • Who to turn to for help when it comes to cost planning a project.
    • What you need to know to draw up a water-tight contract.
    • How to cover yourself when it comes to rectifying defects.
    A white background with a few lines on it
    Instant Access