CASE STUDY UPDATE: Re-Development of Driffield Methodist Church
Richard Hildrick

PROJECT: Re-Development of Driffield Methodist Church

RJH CLIENT: Trustees of Driffield Methodist Church

An aerial view of a building with a lot of windows
 “There has been a very welcome understanding from RJH of our unique funding condition which has necessarily changed the order of approach for the project, that a regular project might not reflect.

RJH also has a robust approach defending our position and achieving our objectives when dealing with all the contractors, quietly and effectively invoked. We also have comfort that there is experience in dispute resolution which should prevent out project requiring those services, and we have benefited from the consistency of working with one person throughout.” 
– Richard Mole. Project Co-Ordinator, Trustees of Driffield Methodist Church
RJH provided Quantity Surveying, Project Management, and Contract Administrator services to Driffield Methodist Church between 2013 and 2019, helping the Trustees to realise their vision of a new modern Church Hall and Community Building, on the site of their existing church which was demolished as part of the project, to make way for the new facility close to Driffield Town Centre in East Yorkshire.

Having initially appointed a local Architect to produce an initial scheme design and obtain planning permission to demolish the existing church and build a completely new combined Church and community building in its place, the trustees needed to move on to turning their vision into reality, and the first step was to understand the costs, risks, and regulatory hurdles involved in realising that vision. 

They appointed RJH to initially prepare a construction cost plan from the planning drawings, before going away to embark upon a challenging process of raising the funding for their £1.5Million project.

As progress on the fund raising progressed, RJH helped the Trustees to assemble a complete project design team comprising a new architectural practice who also took on the role of Principal Designer, a structural engineer, and a mechanical and electrical engineer. As the Church’s appointed Project Manager and Quantity Surveyor, RJH led the design team through the development of the design to meet the Church’s by now further developed brief, at all times keeping an eye on costs, risks, and the need to involve other specialists such as Site Investigation companies, utilities companies, archaeologists, and a ground source heat pump specialist to drill test boreholes to establish the viability of such a sustainable heating solution for the new building.
A further planning submission and approval process was undertaken following the development of the design to a detailed stage, through a series of design team meetings and a detailed process of consultation with all stakeholders, authorities, and ongoing project cost management. Subsequently, a further detailed cost plan was prepared by RJH, involving a large degree of market testing to ensure that the cost plan was both robust and providing the best value for money for the Trustees.

Following the completion of the fund-raising required for the project, RJH prepared tender documents for the demolition phase, which was separated out in order to mitigate the risk of any delays and associated additional cost caused by unforeseen problems, or by any archaeological finds. Yorkshire Demolition and Reclamation Ltd were the successful tenderer, coming in on budget. RJH prepared a contract for the Demolition works, which were subsequently successfully carried out without any problems between September 2018 and February 2019, despite the difficult access into the site and the proximity of adjacent buildings and existing structures.

Construction workers are standing in front of a building that is being demolished
Whilst the demolition works were ongoing on site, a Contractor tender list was drawn up for the new-build phase, and tenders were obtained utilising the Yorhub Framework to ensure that all tenderers were suitably pre-qualified and appropriately vetted as part of the Framework procurement process.

Contractor tenders were obtained in early 2019, which again came in on-budget against the latest RJH cost plan; and in March 2019 RJH drew up Contract documents for the Trustees, and a JCT Building Contract was placed with the Contractor, Hobson & Porter Ltd from Hull.

Construction of the new Church and community building commenced on site in April 2019, and works were completed on site in August 2020, having suffered some delays due to the Covid-19 pandemic restrictions encountered during 2020.

RJH acted as the Church’s Project Manager, Contract Administrator and Quantity Surveyor and has also appointed a Clerk of works to oversee the construction works from a quality perspective.

The project included a fully sustainable Ground Source Heat Pump heating system, which was a Contractor Design Package, along with design of the aluminium curtain walling, windows, and doors, roof trusses, and structural steelwork connections.

The new Church Hall community building was completed by the Contractor, Hobson & Porter, in August 2020 and handed over to a delighted Client. Photographs of the completed building below:

A large red brick building with a roof
A large room with a balcony and chairs
A large brick building with a cross in the window
A man with a beard wearing a white shirt and purple tie
Richard Hildrick - Founder
BSc(Hons) MSc MRICS MCIOB FCIArb

A book titled 10 things you must know to avoid and resolve construction payment disputes
What Is Adjudication in Construction?
By Chris Catalystmarketing August 18, 2026
New to adjudication? This plain-English guide walks subcontractors through what it is, the 28-day timeline, costs, and how to get started.
Why denton contractors trust rjh is written on a red background
August 21, 2024
How a Specialist Subcontractor Benefitted from Adding RJH to Its Team, and Upped its Commercial and Contractual Game Overnight.
A man is giving a presentation to a group of people in a conference room.
August 20, 2024
Our workshops are tailored to each company’s requirements, ensuring you and your team get the most out of it, at a fixed price. One previous attendee said the workshop was: “Vital to anyone working in a commercial or project management role in construction, to understand the workings and thinking of main contractors today.”
An aerial view of a construction site with a lot of buildings and cranes.
By Richard Hildrick August 19, 2024
NEC Contracts Early Warnings v Compensation Events
A man in a yellow jacket is holding a book.
By Richard Hildrick July 24, 2024
Discover how RJH Consulting uses adjudication to recover unpaid contra-charges and deductions for subcontractors, including a recent case worth over £200,000.
A group of construction cranes are silhouetted against a cloudy sky.
By Richard Hildrick June 25, 2024
A cautionary tale from RJH Consulting about a main contractor who levied unfair contra-charges on his subcontractor, and how the dispute was resolved.
A large room with tables and chairs in it.
June 30, 2021
For our latest client, boxxe, we managed a £1m+ office redesign project commercially and operationally. The result was a sleek, modern and on-budget project, completed over a 30-week period.
A construction worker is holding a roll of blueprints.
By RJH Consulting April 15, 2021
Download RJH Consulting's free guide to the 20 most common commercial problems subcontractors face, with practical advice on how to resolve each one.
A man is writing on a piece of paper with a pen.
April 15, 2021
Template Documents to make Subcontractor's lives easier when managing their projects.
Looking up at a group of skyscrapers against a blue sky.
By Richard Hildrick February 10, 2021
Find out how the construction industry's reverse charge VAT rules affect contractors and subcontractors, and what you need to do to stay compliant.